Matjhabeng sewage crisis: 10km of new sewer pipes installed.

Matjhabeng’s sewage crisis persists despite 10km infrastructure push


MATJHABENG – Matjhabeng’s longstanding sewage crisis is far from over, despite a major infrastructure intervention that has seen approximately 10 kilometres of new sewer pipelines installed over the past three months.

The Department of Water and Sanitation (DWS) says progress is being made in tackling the municipality’s failing sewer infrastructure, with projects under way in Thabong, Welkom, Hennenman, Kutlwanong, Bronville, Flamingo Park, Naudeville and Rheeder Park.

However, while the department is highlighting construction milestones, several projects remain behind schedule, raising questions about how quickly residents will see meaningful improvements in sanitation services.

New sewer infrastructure is going into the ground, but residents still face sewage spillages as several projects fall behind schedule and contractors battle delays

The scale of the intervention underlines just how extensive Matjhabeng’s infrastructure problems have become. Years of inadequate maintenance and deteriorating infrastructure have left parts of the municipality struggling with recurring sewage spillages and service interruptions.

According to project reports presented at the Matjhabeng Bulk Sewer Ministerial Intervention meeting on 10 November, approximately 10km of new sewer infrastructure was installed during the preceding three months. The department described this as a substantial improvement in the pace of implementation but acknowledged that work must accelerate to meet agreed deadlines.

Progress comes with delays

Thabong is among the areas receiving attention, with varying levels of progress across four project packages.

The Thabong Extension 3 sewer network project, implemented by Hiwella Trading Enterprise, has been completed, according to the project dashboard.

At Extension 4, Oarabile Plant Hire and Civils had achieved approximately 93% construction progress by 6 November, following the completion of a point repair at the corner of Constantia and Buick Tshabalala. Remaining work is still under way.

However, progress elsewhere is less encouraging.

The Thabong Extension 1 project has installed approximately 120m of pipeline using pipe reaming technology, with completion only scheduled for May 2027.

At Extension 2, just 53m of sleeves had been installed out of a planned 116m, with the project team awaiting approval of a cession agreement affecting one of the work groups.

In Bronville, the sewer network project had reached approximately 32% completion, with 108m of rising main pipeline installed during the reporting period.

Flamingo Park is progressing slower than anticipated following design changes and delays in obtaining approvals. Naudeville has experienced material procurement problems, while the Rheeder Park project is also behind schedule.

In Welkom, the contractor has submitted a recovery programme with a revised completion date of 18 February 2027.

These delays highlight the challenge facing the intervention: infrastructure projects may be gathering momentum, but construction targets and revised completion dates still have to translate into functioning systems.

Pumping stations reach milestones

There have also been developments in the municipality’s pumping station infrastructure.

The project dashboard dated 6 November lists several pumping stations as complete, including Bronville North and South, Major, Power Road, Rheederspark 1 and 2, Traffic, Western, T16, Vida, Akasia, Althea, Ben Regal, Big Frank, Bothaville and Eldorie.

The Thabong 1B Wastewater Treatment Works, which has a capacity of 12 megalitres per day, has reached practical completion, although outstanding snag-list items still need attention.

The Pelatona project has also reached practical completion, with snag-list work continuing.

The department has, however, acknowledged that completing construction is not enough. Infrastructure must still be properly commissioned, made operational and maintained if it is to deliver lasting improvements.

Residents need results, not promises

The intervention involves the DWS, Matjhabeng Local Municipality, Vaal Central Water, the Department of Cooperative Governance and Traditional Affairs, Eskom and other stakeholders.

While the installation of 10km of sewer infrastructure is a significant development, it must be measured against the daily reality of residents who continue to endure sewage-related problems.

For communities that have lived with overflowing sewage, foul smells and repeated service interruptions, construction progress reports offer little comfort unless they result in functioning infrastructure and an end to the spillages.

The real test of the intervention will not be the kilometres of pipes installed or the number of projects marked as complete. It will be whether sewage is effectively removed, treated and prevented from flowing into residential streets and public spaces.

For now, Matjhabeng’s sanitation intervention is showing signs of progress, but the municipality’s sewage crisis remains a test of implementation, accountability and sustained maintenance.